Evaluasi Pelaksanaan Proyek Drainase Dengan Metode CPM Dan PERT
Media Ilmiah Teknik Sipil
,
Volume 9,
pp 44-52; doi:10.33084/mits.v9i1.1884
Abstract: This research purposes to evaluate the implementation of the drainage project in Jl. Mulawarman, Gg. Arjuna, Sepinggan. This research uses the CPM (Critical Path Method) and the PERT (Project Evaluation and Review Technique). Based on the budget plan, time schedule, weekly report, documentation and interview found that the result of the CPM with two critical paths are work activities. The first critical path are: Activity A (Mobilization and Demobilization), Activity C (Landfilling activity), Activity F (Concrete works K-175, Ready Mix). The second critical path are: Activity A (Mobilization and Demobilization), Activity E (Begisting work for black channels), and Activity G (Plain U24 Concrete Iron Works). Meanwhile, the result of PERT has 49% chance to be completed with the project duration of 18 weeks.
Keywords: Activity / concrete / Critical Path / project / CPM / PERT / mobilization and demobilization
Scifeed alert for new publications
Never miss any articles matching your research from any publisher- Get alerts for new papers matching your research
- Find out the new papers from selected authors
- Updated daily for 49'000+ journals and 6000+ publishers
- Define your Scifeed now
Click here to see the statistics on "Media Ilmiah Teknik Sipil" .